Here is the proposed schedule for the upcoming paving projects. Please note that due to weather and other factors, these schedules may vary.
- Mundelein Community Center parking lot—paving complete. The next step in the construction process is seal coating and painting lines. The schedule for seal coating is unknown at this time.
- Maurice Noll Tennis Courts—paving complete, installation of netting posts, painting and fencing date TBD
- Asbury Park, replacing/patching about 5 of the worst areas—walking path patching is about half done. The contractor should finish sometime this week.
- Steeple Chase Cart Path #10–complete.